To date:
Foundation - Complete
Framing - Complete
Window and siding installation - Complete
Electric and Plumbing rough - Complete
Exterior paint - Complete
HVAC - Complete
After inspections for plumbing and electrical rough we will be ready for drywall and all things interior to begin! This puts us into February or March for final completion of both homes.
Interior Finishes
We are excited to announce we have hired a local designer to choose finish outs for this project and give the new homeowner a completely custom feel! Marble tile, brass fixtures, and more are going to give both homes a completely custom look at a great price!
Looking to make a move in 2019 or do you have a client looking for the perfect modern farmhouse? The Thomas Kincheon project will be the perfect home for you or your client.
Call or email us today to schedule a private pre-completion walkthrough of your dream home today.
- The 161 Homes Team